2.27.26

  • Ziggy is working on the updates to the subcontractors listed on the permit per the inspector’s request.

  • Jeff, Aaron, and Sandy met to confirm design decisions and timeline. Plumbing related items are priority, followed by electrical.

  • Aaron communicated via email that design choices that add to the scope will be shared with Ziggy to be priced out and that RH would monitor costs and give feedback to ensure it is in line with expectation.

  • The 12 month timeline was reiterated - anticipated completion & move in, January 2027

  • Aaron started a thread with Jen to confirm loan requirements for material purchases & reimbursement terms.

  • Aaron, Jeff, & Ziggy met on site 2/26 to confirm site conditions, speak about extras, finalize scope, and establish a rough timeline for the coming months.

2.20.26

  • Contractor put up fences around property. Inspection is scheduled for 2.20.26. Approved inspection enables work to progress.

  • Clients are working with Sandy on primary bath, kitchen finishes.

  • Appliances were confirmed and specs shared to all parties 2.15

2.13.26

  • Update for this week.